By Abdulkarim Ibrahim
The Federal Government has said that it is not responsible for non–utilisation of the Owena Multipurpose Dam project since completion in 2007.
This assertion was made known by the Technical Sub-Committee in Evaluation of dams across the country
Director of Dams and Reservoir Operations, Engr. Ali Ibrahim Dalla, who spoke to journalists after carrying out on-the-spot assessment of the Owena Dam, said “the federal government executed its side of the bargain by completing the dam as well as constructing a water treatment plant.
“It was the duty of the Ondo State government to reticulate and deliver water to residents”. He added
The Owena Dam was built to provide water to five local government areas in the state, enabling irrigation for farming and hydroelectric power generation.
The dambhas a storage capacity of 36 million cubic metres, the length is 1.7km and the height is 24 metres but the dam has never been utilised since it was completed.
Dalla said “the committee’s visit was on President Bola Tinubu’s directives to ascertain its health status to avoid a repetition of the devastation that happened in Maiduguri earlier this year.
“the Owena Dam was capable of generating 10 megawatts of electricity.
“We are here for on-the-spot assessment in order to ascertain the health of this Dam arising from what happened in September in Alau dam where flood disaster occurred and destroyed any houses and streets,
“The President saw the need for us to go round the country to evaluate the conditions of our dams to avert similar occurrence. We have gone round and we will make recommendations for a robust plan for government implementation in order to ensure safety of the dams.”